Re-Mark of Runway 17-35

Re-Mark of Runway 17-35


What We're Doing

(Updated 04-10-2018 )

Phase 1: Design and Bid (Completed)

This project is required maintenance and upkeep to re-paint airfield markings on our primary Runway 17-35.  The project has gone out for bid and has been awarded to Custom Paving Maintenance and Safety out of Van Buren, AR.

Phase 2: Construction (Beginning Soon)

Construction will begin soon with primary work to be done at night to provide the least amount of interruption to airport users.  The project is anticipated to take 15 working days.


How We're Paying For It?

The total cost for this project is anticipated to be $96,741.00 and will be paid with local funding.


Latest Project Update